Illustrative example · not a completed transaction

When senior debt may be enough for a Spanish development

This example starts with a project whose budget, contingency and timing may already be covered by senior debt and sponsor equity. The comparison tests whether preferred equity creates value or adds unnecessary cost and control.

Quick answer

Senior debt may be enough when it covers eligible project uses and contingency, the sponsor can fund peak equity and downside liquidity, and the project remains repayable with reasonable headroom. Adding preferred equity should solve a specific capital constraint or fund a higher-value use elsewhere; otherwise it can reduce sponsor profit and add governance complexity.

Before deciding

The questions that change the answer

01

Does senior debt plus sponsor equity fully fund cost and contingency?

02

What is the sponsor's peak cash requirement, including timing gaps?

03

What productive use would be made of cash released by preferred equity?

04

How do sponsor profit, fees and control change under a delayed or lower-value exit?

01

The problem

More leverage can reduce the initial sponsor cheque, but it can also increase total cost, dilute upside and add control rights.

02

The comparison

Model both alternatives against the same budget, sales assumptions and exit date: senior debt plus sponsor equity, and senior debt plus preferred equity plus sponsor equity.

03

The decision rule

The extra layer only makes sense when it closes a real funding gap or releases capital for a use whose risk-adjusted value exceeds its full cost.

04

Start with the simplest funded case

If senior debt plus sponsor equity covers the complete budget, contingency and peak liquidity, first test that structure through downside cases. Only then quantify what an extra capital layer would solve and what it would cost.

Compare before deciding

When an additional capital layer creates value

Compare both structures against the same monthly model rather than assuming that more capital is automatically better.

FindingSenior debt may be enoughPreferred equity may help
Complete fundingSenior and sponsor cash cover all usesThere is a verified capital shortfall
Sponsor liquidityPeak contribution is comfortably availableContribution would exhaust required reserves
Alternative useReleased cash has no higher-value useReleased cash supports another credible project or risk buffer
Project marginExtra priority return materially erodes profitMargin withstands the full waterfall in downside cases
ControlSimple execution is valuableAdditional rights remain workable for delivery

Process

Test the simplest fully funded capital structure first

Only add a new layer after quantifying the funding problem and the value it creates for the sponsor.

  1. STEP 01

    Define the exact need

    Set out what the money pays for, the amount required on each date, the critical milestones and the fallback if the main plan is delayed.

    Output: Funding need and critical-path map

  2. STEP 02

    Reconcile the evidence

    Match the financial model to title, permits, valuation, contracts, paid invoices, debt, sales and the sponsor's proof of equity.

    Output: A consistent lender information pack

  3. STEP 03

    Design the structure

    Size usable proceeds, drawdowns, maturity, repayment, security, covenants and contingency against a base case and a downside case.

    Output: A financeable structure

  4. STEP 04

    Run a selective market process

    Approach only lenders or investors whose mandate fits the location, asset, stage, amount and timetable, using the same information for each.

    Output: Comparable proposals

  5. STEP 05

    Complete diligence and documents

    Coordinate valuation, technical, legal, tax and KYC work, track conditions and confirm that the signed mechanics deliver the expected cash.

    Output: A controlled path to closing and drawdown

Illustrative example · not an offer

Compare two fully funded structures

Illustrative decision framework without assumed market pricing or returns.

Complete project need

€16.0m

Budget, finance costs and contingency.

Senior debt

€10.0m

Same first-ranking facility in both cases.

Option A sponsor equity

€6.0m

Simple structure with all residual economics retained.

Option B preferred / sponsor

€3m / €3m

Additional priority layer and less sponsor cash.

Decision metric

Incremental value

Benefit of released cash less preferred economics and control impact.

Option B releases €3 million, but it is superior only if that liquidity has sufficient value after the preferred investor's full return and the sponsor's reduced residual distributions.

Working tool

Do we actually need preferred equity?

Answer the funding, value and governance questions before approaching an additional capital provider.

01

Funding

  • Complete uses and contingency
  • Senior usable proceeds and drawdowns
  • Peak sponsor cash and reserve
  • Downside completion liquidity
02

Value

  • Use of released sponsor capital
  • Full preferred waterfall
  • Sponsor fees and retained profit
  • Base, early and delayed exit outcomes
03

Execution

  • Senior lender consent
  • Reserved matters and reporting
  • Overrun and cure obligations
  • Exit and manager-change rights

Before signing

Red flags

They do not automatically make a transaction unfinanceable. They show where information must be reconciled, more headroom is required or the structure needs to change.

  • 01

    Preferred equity is added only to maximise a leverage ratio.

  • 02

    The senior-only option is rejected without calculating peak cash.

  • 03

    Released sponsor cash has no identified use or liquidity purpose.

  • 04

    The model excludes fee sharing, minimum multiples or delayed-exit accrual.

  • 05

    The preferred investor's rights conflict with the senior facility or construction decisions.

Apply it to your transaction

A useful first answer starts with specific numbers and dates.

Share the location, stage, total cost, existing debt, invested equity, financing need and expected exit. We will assess fit before opening a process.

Frequently asked questions

Clear answers before you start

Why not always maximise finance?

Because the additional return, control and complexity can cost more than the benefit of contributing less cash.

Can the sponsor keep preferred equity as a contingency only?

A standby commitment may be possible, but availability, commitment cost, conditions and return calculations must be explicit. Do not assume capital can be added instantly after a problem occurs.

Is the lowest sponsor contribution always the best outcome?

No. A lower contribution can reduce residual profit and control. Compare the value of released cash with the full incremental cost and risk.

Can preferred equity be added later?

Potentially, subject to senior-lender consent and the project's performance. Planning the permitted capital structure early avoids an intercreditor problem when cash is urgent.